Planning Commission kisses Mercer Fraser’s ass, yet again

Mercer Fraser Asphalt Plant right above Big Lagoon from county staff report

Taking a page right out of the Republican Senate’s playbook, of making decisions without all the facts, The Humboldt County Planning Commission, as usual, gave Mercer Fraser Company whatever they want.

Our planning commission is a prime example of crony capitalism at its worst. Only Noah Levy ever seems to do any homework before coming to these meetings the others just vote for their developer friends no matter what.

We sure hope Humboldt Baykeeper appeals this to the Supervisors and especially to the California Coastal Commission.

This from Eliane Weinreb on the NCJ Blog:

https://www.northcoastjournal.com/NewsBlog/archives/2018/09/22/planning-commission-approves-mercer-fraser-asphalt-plant-near-big-lagoon

The Humboldt County Planning Commission has approved plans for the continued operation of an asphalt plant less than a half-mile from iconic Big Lagoon despite objections that all the relevant data about the plant has not yet been received and over requests to postpone the decision until next month.

The plant has been operating for several months on an expired permit.

With commissioners Alan Bongio and Brian Mitchell absent, and after a motion to postpone the vote failed, the permit passed with a 4-1 vote, with Noah Levy dissenting.

The plant, operated by Mercer Fraser Co. on land owned by Green Diamond, was initially permitted in March of 2017, with the one-year permit expiring March 18. Mercer Fraser, which is a major contractor for Caltrans, manufactures asphalt used to construct and repair the state’s highways, especially the work which was done throughout the summer on U.S. Highway 101 north of Big Lagoon..

While most people are happy to see roads repaired, not everybody was happy with the location of this particular plant, which is about a half-mile from the waterway.

Few people realized that the plant had, in fact, been operating for more than a year. The initial permit quietly passed through on the commission’s consent calendar in March of 2017. An old lumber mill once operated on the site, which has also apparently been used for other industrial purposes, although the staff report is vague as to just what these were.

Humboldt Baykeeper Director Jennifer Kalt thought it would be prudent to know just what chemicals might be contaminating the site, and in mid-August, asked the Planning Department for further information. She followed her initial queries with a California Public Records Act request and was promised her information by Sept. 24, four days after the commission was scheduled to act on the application. She asked the commission to postpone the hearing until after the requested information has been received.

Kalt also noted that the project area is home to several endangered species including coho and Chinook salmon, and cutthroat trout. She was concerned about possible flood risks and what hazardous materials may exist on the site.

Fifth District Supervisor-elect Steve Madrone spoke from the audience and expressed his concerns about the location of the project within a flood plain. He urged the commission to find a better location — and to postpone the hearing until all the relevant information was available.

With the exception of Levy, the commission did not seem too concerned about these issues. They were more impressed with the statistics provided by Mercer Fraser spokesman Mark Harrison

Levy was concerned about the adequacy of the evacuation plan, noting that if a tsunami-related flood occurred, the company would only have a few minutes’ warning, certainly not enough time to move all that equipment. He initially expressed disbelief with the staff report’s statement that the “project site is not located in a tsunami inundation area,” a statement that the staff planner attributed to the California Department of Conservation.

“What she [Kalt] is asking for is stuff that I would like to know as well: what we know about the contamination of the site,” he said. “This project is in a site where we know the Regional Water Quality Board has some documentation of the contamination. I would like to hear from the Department of Fish and Wildlife about an unexpected risk from a catastrophic event if it were to befall the biological resources just downstream.

“And what about State Parks,” he continued. “Due to the confluence of resources right around here and the risks that are being addressed in some way in the staff report, I think that we should hear from them. Those are the things that make me feel that I don’t have all the information I need to make the decision that this is the best location.”

Was there another possible location for the plant, asked Planning Commissioner Ben Shepherd, considering that it required a site that was already zoned for heavy industry. The county planner said there were not many sites with the necessary zoning and none in the immediate area.

Somebody noted that there were representatives from the Department Fish and Wildlife and the State Parks Department in the audience, but Morris replied that they had not offered to speak during the public comment period and had not officially responded to the county’s project notice.

“We have two options before us,” said Shepherd. “We can postpone the project to provide more information, or we can choose to vote it up or down. I’m leaning toward postponement because we had a number of people who expressed, ‘not enough information.’ … I want the public to be more comfortable with this and not go through a series of appeals.”

Shepherd moved to continue to the project to the commission’s Oct. 18 meeting. Levy seconded the move. Shepherd then added that he supported the project, that it would save trucks from having to traverse the streets of Eureka, and that most mills were already close to Redwood National Park and herds of elk.

The commissioners voted down the postponement 3-2, with Morris, Newman and Edmonds dissenting.

Edmonds then moved to approve the project and it passed with Levy as the sole dissenter.

The project approval can be appealed to the California Coastal Commission and to the Humboldt County Board of Supervisors.

2 thoughts on “Planning Commission kisses Mercer Fraser’s ass, yet again

  1. Did they already forget Ryan Sundberg’s defeat courtesy of the voters? Dumbass Virginia Bass, Racist Rex Bonehead, and Estelle Fennell can share Ryan Dumberg’s fate, if they wish. 🐘🚫

    Liked by 1 person

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google photo

You are commenting using your Google account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s